Terminal renovations and improve customer accessibility
Federal contribution
$550,000
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2020
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Timmins
- Construction start
- Feb 6, 2023(actual)
- Construction end
- Mar 7, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast Oct 17, 2022
- Construction end5 months lateforecast Oct 6, 2023
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55079 in the federal list. How to read these figures.