Highway 7/8 Cycling and Pedestrian Bridge
Federal contribution
$3.8M
$3,800,000
Federal share40%
of $9.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2020
20212022202320242025
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Feb 13, 2023(actual)
- Construction end
- Jul 23, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast Nov 1, 2022
- Construction end3 months lateforecast May 1, 2025