Highway 7/8 Cycling and Pedestrian Bridge

Waterloo, Ontario

completeActive TransportationPTIS
Federal contribution
$3.8M
$3,800,000
Federal share40%

of $9.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2020
20212022202320242025
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Feb 13, 2023(actual)
Construction end
Jul 23, 2025(actual)

Against the original forecast

  • Construction start3 months lateforecast Nov 1, 2022
  • Construction end3 months lateforecast May 1, 2025

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55100 in the federal list. How to read these figures.