Market Trail to ION Light Rail Transit
Federal contribution
$1.1M
$1,124,000
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2020
2020202220242026
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- May 1, 2020(actual)
- Construction end
- Nov 28, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Jan 1, 2020
- Construction end5 weeks earlyforecast Dec 31, 2025
Also in Waterloo