Relocation of the Downtown Terminal
Federal contribution
$100,020
Federal share42%
of $238.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Sault Ste. Marie
- Construction start
- Sep 2, 2020(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start8 months earlyforecast May 1, 2021
- Construction end6 months earlyforecast Dec 31, 2022
Also in Sault Ste. Marie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55106 in the federal list. How to read these figures.