Iron Horse Trail Improvements
Federal contribution
$264,356
Federal share40%
of $660.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2020
2021202220232024
Built
Approved 7 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Aug 22, 2022(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2022