University of Waterloo Transit Shelter Canopy

Waterloo, Ontario

completePublic TransitPTIS
Federal contribution
$1.5M
$1,500,000
Federal share40%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2020
20212022
Built

Approved 7 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
May 1, 2020(actual)
Construction end
Jan 3, 2022(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 15, 2020
  • Construction end4 weeks earlyforecast Jan 31, 2022

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55122 in the federal list. How to read these figures.