Back to projects

Bus Storage Shelter

Machin, Ontario

completePublic TransitPTIS
Federal contribution
$8,758
Federal share40%

of $21.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 27, 2020
20202021
Built

Approved 10 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
Municipality of Machin
Construction start
Jan 23, 2020(actual)
Construction end
Sep 15, 2021(actual)

Against the original forecast

  • Construction end4 months earlyforecast Dec 31, 2021

Also in Machin