Rebuilding V.Bay Dock Access
Federal contribution
$87,500
Federal share51%
of $172.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 19, 2021
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Machin
- Construction start
- Jul 1, 2021(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 31, 2021
- Construction end2 months earlyforecast Sep 30, 2021
Also in Machin
- Upgrade of the Machin Water Treatment Plant$88.4K
- Flood Mitigation for Berglund Road$80.0K
- Vermilion Bay Water Treatment Plant, 8 Bay Street, Vermilion Bay Ontario. System control and Data acquisition upgrading serving 218 services or approximately 550 people.$64.2K
- Purchase One New Replacement Bus$51.6K
- Bus Storage Shelter$8.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57968 in the federal list. How to read these figures.