Vermilion Bay Water Treatment Plant, 8 Bay Street, Vermilion Bay Ontario. System control and Data acquisition upgrading serving 218 services or approximately 550 people.

Machin, Ontario

completeDrinking WaterCWWF
Federal contribution
$64,193
Federal share47%

of $135.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Machin
Construction start
Jun 15, 2017(actual)
Construction end
Dec 12, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast Dec 12, 2016
  • Construction end7 months lateforecast May 26, 2017

Also in Machin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48589 in the federal list. How to read these figures.