Back to projects

Specialized Transit Service Expansion and Accessibility Improvements to existing stops

Port Hope, Ontario

completePublic TransitPTIS
Federal contribution
$26,656
Federal share40%

of $66.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 18, 2020
2021
Built

Approved 2 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
Municipality of Port Hope
Construction start
Jun 6, 2021(actual)
Construction end
Nov 26, 2021(actual)

Also in Port Hope