Specialized Transit Service Expansion and Accessibility Improvements to existing stops
Federal contribution
$26,656
Federal share40%
of $66.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 18, 2020
2021
Built
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Municipality of Port Hope
- Construction start
- Jun 6, 2021(actual)
- Construction end
- Nov 26, 2021(actual)
Also in Port Hope
- Upgrades to Port Hope Water Pollution Control Plant$4.9M
- Joint Operations Centre$1.7M
- Dorset Street Standpipe Replacement - Phase 1$1.4M
- Construction of a New Seniors/Multipurpose Community Centre as an addition at the Town Park Recreation Centre$1.2M
- Sanitary Sewer Twinning of the gravity sewer from Hope Street to the Sewage Treatment Plant to mitigate by-pass during wet weather events$772.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55180 in the federal list. How to read these figures.