Back to projects

Replacement of Paratransit vehicles

St. Catharines, Ontario

completePublic TransitPTIS
Federal contribution
$403,200
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2020
2020202120222023
Built

Approved 5 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Feb 15, 2021(actual)
Construction end
Dec 31, 2022(actual)

Also in St. Catharines

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55216 in the federal list. How to read these figures.