Okanagan-Similkameen - Willowbrook Water Treatment - Chlorine Contact System
Okanagan-Similkameen, British Columbia
Federal contribution
$89,252
Federal share60%
of $148.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
Built
Approved 4 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Regional District of Okanagan-Similkameen
- Construction start
- Jun 19, 2020(actual)
- Construction end
- Aug 28, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2020
- Construction end4 weeks lateforecast Jul 30, 2020