Back to projects

Okanagan-Similkameen - Willowbrook Water Treatment - Chlorine Contact System

Okanagan-Similkameen, British Columbia

completeDrinking WaterRNIS
Federal contribution
$89,252
Federal share60%

of $148.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
Built

Approved 4 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 19, 2020(actual)
Construction end
Aug 28, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2020
  • Construction end4 weeks lateforecast Jul 30, 2020

Also in Okanagan-Similkameen

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56201 in the federal list. How to read these figures.