Okanagan-Similkameen - Naramata Recreation Access & Enhancement

Okanagan-Similkameen, British Columbia

completeRecreationCCRIS
Federal contribution
$124,000
Federal share40%

of $310.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Oct 15, 2020(actual)
Construction end
Dec 31, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Dec 1, 2021