Upper Similkameen Indian Band - Chuchuwayha Hall
Okanagan-Similkameen, British Columbia
Federal contribution
$1.5M
$1,504,670
Federal share100%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2021
202220232024
Built
Approved 7 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Upper Similkameen Indian Band
- Construction start
- Mar 1, 2022(actual)
- Construction end
- Jul 31, 2024(actual)
Against the original forecast
- Construction start3 months earlyforecast Jun 1, 2022
- Construction end4 weeks lateforecast Jun 30, 2024
Also in Okanagan-Similkameen
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60564 in the federal list. How to read these figures.