Chase - Wilson Park Footbridge
Federal contribution
$60,000
Federal share40%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
2021
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Village of Chase
- Construction start
- Jul 5, 2021(actual)
- Construction end
- Nov 30, 2021(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 1, 2021
- Construction end4 weeks earlyforecast Dec 31, 2021
Also in Chase
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56231 in the federal list. How to read these figures.