Water Supply Line Upgrade
Federal contribution
$3.1M
$3,131,306
Federal share40%
of $7.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Rimouski
- Construction start
- Apr 6, 2021(actual)
- Construction end
- Jul 8, 2024(actual)
Against the original forecast
- Construction end6 months earlyforecast Dec 31, 2024