Water Supply Line Upgrade

Rimouski, Quebec

completeDrinking WaterGIS
Federal contribution
$3.1M
$3,131,306
Federal share40%

of $7.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021202220232024
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Rimouski
Construction start
Apr 6, 2021(actual)
Construction end
Jul 8, 2024(actual)

Against the original forecast

  • Construction end6 months earlyforecast Dec 31, 2024