Back to projects

Renewal of water pipes

Rimouski, Quebec

completeDrinking WaterCWWF
Federal contribution
$3.1M
$3,062,413
Federal share50%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 3, 2017
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Rimouski
Construction start
May 11, 2017(actual)
Construction end
Oct 27, 2017(actual)

Against the original forecast

  • Construction start13 months lateforecast Apr 1, 2016
  • Construction end5 months earlyforecast Mar 31, 2018

Also in Rimouski

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48864 in the federal list. How to read these figures.