Renewal of water pipes
Federal contribution
$3.1M
$3,062,413
Federal share50%
of $6.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 3, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Rimouski
- Construction start
- May 11, 2017(actual)
- Construction end
- Oct 27, 2017(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end5 months earlyforecast Mar 31, 2018
Also in Rimouski
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48864 in the federal list. How to read these figures.