Swimming pool major retrofit
Federal contribution
$2.3M
$2,304,800
Federal share66%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Rimouski
- Construction start
- Apr 5, 2021(actual)
- Construction end
- Feb 10, 2022(actual)
Against the original forecast
- Construction end5 weeks lateforecast Jan 7, 2022
Also in Rimouski
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58892 in the federal list. How to read these figures.