Water Systems Upgrades
Federal contribution
$254,970
Federal share40%
of $637.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 15, 2020
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Victoriaville
- Construction start
- Jul 6, 2020(actual)
- Construction end
- Sep 25, 2020(actual)
Also in Victoriaville
- Protection and securing of the drinking water supply in the Beaudet Reservoir of the City of Victoriaville.$16.0M
- Victoriaville Performing Arts Centre$8.0M
- Upgrade of equipment of treatment of wastewater in the STEP$2.4M
- Replacement of ventilation systems serving the medical imaging sector (radiology and nuclear medicine)$1.4M
- Upgrade of the Arthabaska community center$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56258 in the federal list. How to read these figures.