Capital Regional District - Mayne Island Regional Trail Phase 1 Development
Federal contribution
$1.5M
$1,515,556
Federal share40%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Regional District of Capital
- Construction start
- Nov 17, 2022(actual)
- Construction end
- Oct 31, 2024(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Dec 7, 2022
- Construction end4 months lateforecast Jun 30, 2024
Also in Capital
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56313 in the federal list. How to read these figures.