Capital Regional District - Mayne Island Regional Trail Phase 1 Development

Capital, British Columbia

completeActive TransportationCCRIS
Federal contribution
$1.5M
$1,515,556
Federal share40%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 3, 2020
20212022202320242025
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Nov 17, 2022(actual)
Construction end
Oct 31, 2024(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Dec 7, 2022
  • Construction end4 months lateforecast Jun 30, 2024