Capital - Drake Road Trail Upgrade
Federal contribution
$72,102
Federal share80%
of $90.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Regional District of Capital
- Construction start
- Oct 25, 2021(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 1, 2021
Also in Capital
- Wastewater Treatment for the Capital Regional District (Victoria)$120.0M
- Feasibility Studies for Wastewater Treatment in the CRD$3.3M
- Capital - Magic Lake Estates Wastewater Upgrades$3.1M
- Capital - CRD Public Electric Vehicle Charging Network$1.7M
- Capital Regional District - Mayne Island Regional Trail Phase 1 Development$1.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60513 in the federal list. How to read these figures.