Capital - Magic Lake Estates Wastewater Upgrades
Federal contribution
$3.1M
$3,083,740
Federal share40%
of $7.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2021
2022202320242025
Built
Approved 8 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Regional District of Capital
- Construction start
- Jun 28, 2023(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 15, 2023
Also in Capital
- Wastewater Treatment for the Capital Regional District (Victoria)$120.0M
- Feasibility Studies for Wastewater Treatment in the CRD$3.3M
- Capital - CRD Public Electric Vehicle Charging Network$1.7M
- Capital Regional District - Mayne Island Regional Trail Phase 1 Development$1.5M
- Capital - Drake Road Trail Upgrade$72.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60292 in the federal list. How to read these figures.