Water Systems Upgrades

Tring-Jonction, Quebec

completeWastewaterGIS
Federal contribution
$767,454
Federal share40%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2020
2021
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Tring-Jonction
Construction start
Sep 24, 2020(actual)
Construction end
Nov 30, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 10, 2020
  • Construction end5 months lateforecast Jun 30, 2021

Also in Tring-Jonction

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56329 in the federal list. How to read these figures.