Renewal of water pipes

Tring-Jonction, Quebec

completeDrinking WaterCWWF
Federal contribution
$453,158
Federal share50%

of $906.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Tring-Jonction
Construction start
Jun 21, 2017(actual)
Construction end
Nov 6, 2017(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2018

Also in Tring-Jonction

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49023 in the federal list. How to read these figures.