Water Systems Upgrades
Federal contribution
$1.6M
$1,640,961
Federal share50%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Tring-Jonction
- Construction start
- Jul 13, 2017(actual)
- Construction end
- Nov 17, 2017(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end16 months earlyforecast Mar 31, 2019
Also in Tring-Jonction
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49027 in the federal list. How to read these figures.