Water Systems Upgrades

Saint-Célestin, Quebec

completeWastewaterGIS
Federal contribution
$685,822
Federal share40%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 15, 2020
20212022
Built

Approved 4 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Saint-Célestin
Construction start
Jun 27, 2022(actual)
Construction end
Nov 15, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2022
  • Construction end7 weeks earlyforecast Dec 31, 2022

Also in Saint-Célestin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56458 in the federal list. How to read these figures.