Water Systems Upgrades
Federal contribution
$685,822
Federal share40%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 15, 2020
20212022
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Saint-Célestin
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Nov 15, 2022(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2022
- Construction end7 weeks earlyforecast Dec 31, 2022
Also in Saint-Célestin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56458 in the federal list. How to read these figures.