Back to projects

Drinking water upgrade

Saint-Célestin, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.0M
$1,039,680
Federal share38%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
201720182019
Built

Approved 4 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Saint-Célestin
Construction start
Oct 30, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017

Also in Saint-Célestin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48406 in the federal list. How to read these figures.