Water Pipe Replacement

Saint-Célestin, Quebec

completeDrinking WaterCWWF
Federal contribution
$352,952
Federal share50%

of $705.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
2018
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Saint-Célestin
Construction start
Oct 30, 2017(actual)
Construction end
Nov 7, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2019