Replacing Blowers
Federal contribution
$1.3M
$1,322,225
Federal share40%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 12, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Trois-Rivières
- Construction start
- May 1, 2021(actual)
- Construction end
- Mar 2, 2025(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 25, 2021
- Construction end2 months lateforecast Dec 31, 2024
Also in Trois-Rivières