Water Systems Upgrades
Federal contribution
$2.0M
$1,993,163
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
202120222023
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Thetford Mines
- Construction start
- Sep 1, 2020(actual)
- Construction end
- Dec 16, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Nov 18, 2022
Also in Thetford Mines
- Upgrades to Thetford Mines water treatment and distribution system$22.3M
- Repair of generators and increase in the capacity of the emergency electrical network$1.5M
- Retrofit and updrage the Promutuel Room$718.5K
- Program for the renewal of drinking water and wastewater pipes$411.7K
- Infrastructure work for the 2018 Quebec Games$375.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56576 in the federal list. How to read these figures.