Repair of generators and increase in the capacity of the emergency electrical network

Thetford Mines, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$1.5M
$1,517,909
Federal share80%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 1, 2021(actual)
Construction end
May 1, 2024(actual)

Also in Thetford Mines