Retrofit and updrage the Promutuel Room
Federal contribution
$718,500
Federal share34%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Thetford
- Construction start
- Aug 21, 2021(actual)
- Construction end
- Apr 29, 2022(actual)
Against the original forecast
- Construction end3 months lateforecast Jan 31, 2022
Also in Thetford Mines
- Upgrades to Thetford Mines water treatment and distribution system$22.3M
- Water Systems Upgrades$2.0M
- Repair of generators and increase in the capacity of the emergency electrical network$1.5M
- Program for the renewal of drinking water and wastewater pipes$411.7K
- Infrastructure work for the 2018 Quebec Games$375.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59014 in the federal list. How to read these figures.