Water Systems Upgrades
Federal contribution
$3.1M
$3,122,952
Federal share40%
of $7.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2020
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Laval
- Construction start
- May 18, 2020(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 14, 2020
- Construction end3 months earlyforecast Mar 31, 2025
Also in Laval
- The Société de transport de Laval garage expansion (Phase IV)$85.1M
- Acquisition of 94 Electric Buses$59.5M
- Updating drinking water treatment plants in Laval$46.8M
- Stabilization and revitalization work on the shore and Boulevard des Mille-Îles between Highway 25 and the eastern tip of Laval Island$25.3M
- Backflow controls of Monty sector - Laval$12.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56726 in the federal list. How to read these figures.