Back to projects

Construction of a UV Disinfection Building

Grand Falls-Windsor, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$904,124
Federal share40%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
20212022
Built

Approved 11 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Grand Falls-Windsor
Construction start
Aug 2, 2021(actual)
Construction end
Nov 10, 2022(actual)

Against the original forecast

  • Construction start9 months earlyforecast May 1, 2022
  • Construction end5 months earlyforecast Mar 31, 2023

Also in Grand Falls-Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56760 in the federal list. How to read these figures.