Rehabilitation of 3 Lift Stations

Badger, Newfoundland and Labrador

completeWastewaterGIS
Federal contribution
$237,670
Federal share40%

of $594.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2021
202120222023
Built

Approved 12 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Badger
Construction start
Aug 7, 2022(actual)
Construction end
Jan 22, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2022
  • Construction end3 weeks lateforecast Dec 31, 2022