Partial Water and Sewer Replacement - Sunset Drive

Badger, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$63,213
Federal share40%

of $158.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
2022
Built

Approved 2 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Badger
Construction start
Sep 19, 2022(actual)
Construction end
Nov 4, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2022
  • Construction end2 months lateforecast Aug 31, 2022