Partial Water and Sewer Replacement - Sunset Drive
Badger, Newfoundland and Labrador
Federal contribution
$63,213
Federal share40%
of $158.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2022
2022
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Badger
- Construction start
- Sep 19, 2022(actual)
- Construction end
- Nov 4, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2022
- Construction end2 months lateforecast Aug 31, 2022
Also in Badger
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61547 in the federal list. How to read these figures.