Replacement of Water and Sewer Infrastructure along the Trans-Canada Highway
Badger, Newfoundland and Labrador
Federal contribution
$465,907
Federal share50%
of $931.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Badger
- Construction start
- Jun 22, 2018(actual)
- Construction end
- Nov 20, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2018
- Construction end11 months lateforecast Dec 31, 2018