Back to projects

Replacement of Water and Sewer Infrastructure along the Trans-Canada Highway

Badger, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$465,907
Federal share50%

of $931.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Badger
Construction start
Jun 22, 2018(actual)
Construction end
Nov 20, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2018
  • Construction end11 months lateforecast Dec 31, 2018