Schedule
Announced and approvedJun 18, 2021
2021
Built
Approved 12 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Carmanville
- Construction start
- Aug 11, 2021(actual)
- Construction end
- Nov 18, 2021(actual)
Against the original forecast
- Construction end7 months earlyforecast Jun 30, 2022