Water and Sewer Phase 2
Carmanville, Newfoundland and Labrador
Federal contribution
$450,649
Federal share50%
of $906.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Carmanville
- Construction start
- Aug 28, 2017(actual)
- Construction end
- Sep 15, 2018(actual)
Against the original forecast
- Construction end6 months earlyforecast Mar 31, 2019
Also in Carmanville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47013 in the federal list. How to read these figures.