Back to projects

Water and Sewer Services Phase 4

Carmanville, Newfoundland and Labrador

approvedDrinking WaterGIS
Federal contribution
$439,383
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
202420252026
BuiltForecast

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carmanville
Construction start
May 26, 2026(forecast)
Construction end
Aug 5, 2026(forecast)

Also in Carmanville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67322 in the federal list. How to read these figures.