Water and Sewer Services Phase 4
Carmanville, Newfoundland and Labrador
Federal contribution
$439,383
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
202420252026
BuiltForecast
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Carmanville
- Construction start
- May 26, 2026(forecast)
- Construction end
- Aug 5, 2026(forecast)
Also in Carmanville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67322 in the federal list. How to read these figures.