Transit Service Strategy Implementation and Specialized Transit Services
Federal contribution
$558,600
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 18, 2020
today
20212023202520272029
BuiltForecast
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Town of Halton Hills
- Construction start
- Feb 11, 2021(actual)
- Construction end
- Dec 27, 2028(forecast)
Also in Halton Hills
- Improvements to Glen Lawson Road and Third Line$937.5K
- Installation of New 825mm Stormwater Sewer and Water Quality Treatment Unit on Armstrong Avenue$415.0K
- Maple Avenue Bike Lanes & Multi-Use Path$214.6K
- Credit Valley Trail - Upper Canada College Phase 1$149.2K
- Purchase of two (2) ActiVan Transit Vehicles$130.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56939 in the federal list. How to read these figures.