Maple Avenue Bike Lanes & Multi-Use Path

Halton Hills, Ontario

completeActive TransportationCVRIS
Federal contribution
$214,574
Federal share80%

of $268.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Halton Hills
Construction start
Jul 5, 2021(actual)
Construction end
Oct 29, 2021(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2021