Credit Valley Trail - Upper Canada College Phase 1

Halton Hills, Ontario

completeActive TransportationATF
Federal contribution
$149,160
Federal share45%

of $328.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2024
20232024
Built

Approved 2.2 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Halton Hills
Construction start
Jan 9, 2023(actual)
Construction end
Oct 6, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Aug 1, 2022
  • Construction end3 months earlyforecast Dec 31, 2023

Also in Halton Hills

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63663 in the federal list. How to read these figures.