Vancouver - Sewage Heat Recovery Expansion Project for Vancouver False Creek NEU

Vancouver, British Columbia

completeWastewaterGIS
Federal contribution
$5.6M
$5,572,000
Federal share40%

of $13.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2020
20212022202320242025
Built

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Vancouver
Construction start
Jun 28, 2021(actual)
Construction end
Dec 6, 2024(actual)

Against the original forecast

  • Construction start6 months earlyforecast Dec 15, 2021