Vancouver - Sewage Heat Recovery Expansion Project for Vancouver False Creek NEU
Federal contribution
$5.6M
$5,572,000
Federal share40%
of $13.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2020
20212022202320242025
Built
Approved 7 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Vancouver
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Dec 6, 2024(actual)
Against the original forecast
- Construction start6 months earlyforecast Dec 15, 2021
Also in Vancouver
- Millennium Line Broadway Extension (TransLink)$888.4M
- Vancouver Convention and Exhibition Centre Expansion$222.5M
- Seismic Upgrade and Rehabilitation of Cambie Street Bridge in Vancouver, British Columbia$84.4M
- Rapid Transit Systems Rehabilitation and Maintenance$46.2M
- Rapid Transit Fleet Expansion - SkyTrain Network$44.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56996 in the federal list. How to read these figures.