Kamloops - Canada Games Aquatic Centre Rehabilitation
Federal contribution
$1.4M
$1,370,328
Federal share40%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2020
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Kamloops
- Construction start
- Jun 22, 2020(actual)
- Construction end
- Dec 11, 2020(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Jan 30, 2021
Also in Kamloops
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57004 in the federal list. How to read these figures.