Mayo Water Treatment Plant Wellfield Expansion

Mayo, Yukon

completeDrinking WaterGIS
Federal contribution
$552,600
Federal share75%

of $736.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 4, 2021
20212022202320242025
Built

Approved 11 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Mayo
Construction start
Aug 1, 2021(actual)
Construction end
Mar 25, 2025(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 20, 2020
  • Construction end5 months earlyforecast Aug 31, 2025