Atikokan Sewage Works Rehabilitation

Atikokan, Ontario

completeDrinking WaterGIS
Federal contribution
$1.2M
$1,166,964
Federal share40%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 16, 2020
2021
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of Atikokan
Construction start
May 10, 2021(actual)
Construction end
Sep 24, 2021(actual)

Against the original forecast

  • Construction end3 months earlyforecast Dec 31, 2021

Also in Atikokan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57328 in the federal list. How to read these figures.