AGH Extended Care Wing HVAC & Sprinkler System
Federal contribution
$1.5M
$1,488,560
Federal share80%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 16, 2021
2022202320242025
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Atikokan General Hospital - Atikokan General Hospital
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Aug 11, 2025(actual)
Against the original forecast
- Construction end8 months earlyforecast Mar 31, 2026