Replacement of O'Brien Street Watermain
Federal contribution
$1.8M
$1,750,000
Federal share40%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
202320242025
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Township of Atikokan
- Construction start
- Jun 1, 2024(actual)
- Construction end
- Sep 30, 2025(forecast)