Rural Municipality of Porcupine No. 395, Farley Bridge Replacement
Porcupine No. 395, Saskatchewan
Federal contribution
$166,650
Federal share17%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 9, 2021
20212022
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Municipality of Porcupine No. 395
- Construction start
- Nov 1, 2021(actual)
- Construction end
- Jun 13, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Mar 31, 2022
Also in Porcupine No. 395
- RM of Porcupine No. 395, Wolstenholme Bridge$166.7K
- Rural Municipality of Porcupine No. 395, Copeau Bridge Replacement$150.0K
- Hintz Bridge over the Prairie River in the Rural Municipality of Porcupine No. 395$116.7K
- North South Peggs Bridge over McKillop Creek in the Rural Municipality of Porcupine$115.2K
- Belchamber Bridge over Shand Creek in the Regional Municipality of Porcupine No. 395$114.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57337 in the federal list. How to read these figures.